action against the subcontractor, supplier or design professional related to the constructional defect unless the contractor demonstrates that, after making a good faith effort, he was unable to identify the subcontractor, supplier or design professional who he believes is responsible for the defect within the time provided pursuant to subsection 1.
3. Except as otherwise provided in subsection 4, not later than 30 days after receiving notice from the contractor pursuant to this section, the subcontractor, supplier or design professional shall inspect the alleged constructional defect in accordance with subsection 1 of NRS 40.6462 and provide the contractor with a written statement indicating:
(a) Whether the subcontractor, supplier or design professional has elected to repair the defect for which the contractor believes the subcontractor, supplier or design professional is responsible; and
(b) If the subcontractor, supplier or design professional elects to repair the defect, an estimate of the length of time required for the repair, and at least two proposed dates on and times at which the subcontractor, supplier or design professional is able to begin making the repair.
4. If the notice of a constructional defect forwarded by the contractor was given pursuant to subsection 4 of NRS 40.645 and the contractor provides a disclosure of the notice of the alleged common constructional defects to the unnamed owners to whom the notice may apply pursuant to NRS 40.6452:
(a) The contractor shall, in addition to the notice provided pursuant to subsection 1, upon receipt of a request for an inspection, forward a copy of the request to or notify each subcontractor, supplier or design professional who may be responsible for the alleged defect of the request not later than 5 working days after receiving such a request; and
(b) Not later than 20 days after receiving notice from the contractor of such a request, the subcontractor, supplier or design professional shall inspect the alleged constructional defect in accordance with subsection 2 of NRS 40.6462 and provide the contractor with a written statement indicating:
(1) Whether the subcontractor, supplier or design professional has elected to repair the defect for which the contractor believes the subcontractor, supplier or design professional is responsible; and
(2) If the subcontractor, supplier or design professional elects to repair the defect, an estimate of the length of time required for the repair, and at least two proposed dates on and times at which the subcontractor, supplier or design professional is able to begin making the repair.
5. If a subcontractor, supplier or design professional elects to repair the constructional defect, the contractor or claimant may hold the subcontractor liable for any repair which does not eliminate the defect.
(Added to NRS by 2003, 2035)
NRS 40.6462 Access to residence or appurtenance with alleged defect after notice of defect is given; effect on owners who did not provide notice.
1. Except as otherwise provided in subsection 2, after notice of a constructional defect is given to a contractor pursuant to NRS 40.645, the claimant shall, upon reasonable notice, allow the contractor and each subcontractor, supplier or design professional who may be responsible for the alleged defect reasonable access to the residence or appurtenance that is the subject of the notice to determine the nature and extent of a constructional defect and the nature and extent of repairs that may be necessary. To the extent possible, the persons entitled to inspect shall coordinate and conduct the inspections in a manner which minimizes the inconvenience to the claimant.
2. If notice is given to the contractor pursuant to subsection 4 of NRS 40.645, the contractor and each subcontractor, supplier or design professional who may be responsible for the defect do not have the right to inspect the residence or appurtenance of an owner who is not named in the notice unless the owner requests the inspection in the manner set forth in NRS 40.6452. If the owner does not request the inspection, the owner shall be deemed not to have provided notice pursuant to NRS 40.645.
(Added to NRS by 2003, 2036)
NRS 40.647 Claimant required to allow inspection of and reasonable opportunity to repair defect; effect of noncompliance.
1. Except as otherwise provided in NRS 40.6452, after notice of a constructional defect is given pursuant to NRS 40.645, before a claimant may commence an action or amend a complaint to add a cause of action for a constructional defect against a contractor, subcontractor, supplier or design professional, the claimant must:
(a) Allow an inspection of the alleged constructional defect to be conducted pursuant to NRS 40.6462; and
(b) Allow the contractor, subcontractor, supplier or design professional a reasonable opportunity to repair the constructional defect or cause the defect to be repaired if an election to repair is made pursuant to NRS 40.6472.
2. If a claimant commences an action without complying with subsection 1 or NRS 40.645, the court shall:
(a) Dismiss the action without prejudice and compel the claimant to comply with those provisions before filing another action; or
(b) If dismissal of the action would prevent the claimant from filing another action because the action would be procedurally barred by the statute of limitations or statute of repose, the court shall stay the proceeding pending compliance with those provisions by the claimant.
(Added to NRS by 2003, 2039)
NRS 40.6472 Response to notice of defect: Time for sending; content; effect of election to repair or not to repair.
1. Except as otherwise provided in NRS 40.670 and 40.672 and NRS 40.6452, a written response must be sent by certified mail, return receipt requested, to a claimant who gives notice of a constructional defect pursuant to NRS 40.645:
(a) By the contractor not later than 90 days after the contractor receives the notice; and
(b) If notice was sent to a subcontractor, supplier or design professional, by the subcontractor, supplier or design professional not later than 90 days after the date that the subcontractor, supplier or design professional receives the notice.
2. The written response sent pursuant to subsection 1 must respond to each constructional defect in the notice and:
(a) Must state whether the contractor, subcontractor, supplier or design professional has elected to repair the defect or cause the defect to be repaired. If an election to repair is included in the response and the repair will cause the claimant to move from his home during the repair, the election must also include monetary compensation in an amount reasonably necessary for temporary housing or for storage of household items, or for both, if necessary.
(b) May include a proposal for monetary compensation, which may include contribution from a subcontractor, supplier or design professional.
(c) May disclaim liability for the constructional defect and state the reasons for such a disclaimer.
3. If the claimant is a homeowners’ association, the association shall send a copy of the response to each member of the association not later than 30 days after receiving the response.
4. If the contractor, subcontractor, supplier or design professional has elected not to repair the constructional defect, the claimant or contractor may bring a cause of action for the constructional defect or amend a complaint to add a cause of action for the constructional defect.
5. If the contractor, subcontractor, supplier or design professional has elected to repair the constructional defect, the claimant must provide the contractor, subcontractor, supplier or design professional with a reasonable opportunity to repair the constructional defect.
(Added to NRS by 2003, 2037)